Deepwater Oil Spill - a slight change in plan

I have not had a chance to read the BP report on the Deepwater Horizon disaster yet, and due to a couple of other activities (I returned to the USA today) have had only a limited amount of time to catch up on the current plans for abandoning the well, which were reviewed by Admiral Allen at his press conference .

One of the points that he mentioned however, that I thought might be worth discussing a little, is the plan to use the Development Driller II that is connected to the original well at the moment, to complete much of the plugging and abandonment procedures. I will go through that process again in a later post, but one of the things that the Admiral noted today was that the new process would be as follows:
If you remember, the DDII was drilling the second relief well. They came off of that wellhead and took the Blow Out Preventer, and that is the Blow Out Preventer that is now on the well. So they are hooked up to the new Blow Out Preventer over the well, just the same as the original rig would have been, had it still been there.

So they can go down through the well and perforate the casing above the cement and actually cement in the annulus from the top, because they're already there and available to do it. And then shortly thereafter, we will finish the relief well from the bottom with Development Driller III, which was always drilling the first relief well, and they'll do it on the bottom.


Now the point is that to gain access to the top of the cement that was pumped down the production casing, the DD2 is going to have to send tools down to the top of the projected cement and then perforate the casing to inject either mud or cement into that area of the annulus.

Here is where I have the current question. There was some 3,000 ft of drill pipe in the well below the original BOP, that wasn’t there when the BOP was removed. The question becomes, when did it fall into the well? Was it before the cement was injected (in which case the falling DP could have done some damage to the shoe, but all is now hidden, including the DP, in the cement injected) or did the DP fall later during the removal events that took the original BOP from the well.

In that case the DP could have fallen on top of the cement, could have damaged the casing in the process, and would, quite likely be distributed within the production casing so that it will make it difficult for the current operators to get their tool down to the required perforation and injection zone, with the DP in the way.

This could very well explain why they want to get the DP out of the hole using a fishing expedition, but it could be that they won’t find it, since it fell earlier and has been buried in the cement fill. At which point they can then proceed to do the final plug and abandon, following the path that the Admiral outlined. There is, however, no hurry at the moment, and the relief well could now not be completed until the end of the month.

For those wishing to read and comment on the report that BP have just issued on the originating events, that report can be accessed at the BP internal investigation website, and your comments are welcome.

Read more!

Thursday, August 26, 2010

Deepwater Oil Spill - Recovering pipe

The problem with not watching the video feeds from the ROVs at the Deepwater site on a very regular schedule is that it becomes hard to define if anything has changed since the last time you looked. At 11 pm Central tonight, for example, the feed has switched back from the downhole camera to the ROV camera on the Boa Sub C ROV1, and the borehole feed shows that the pipe containing the camera seems to be dangling in the water, as it has been some time ago. So it was not clear from the suggested cameras as to the current status of the fishing attempts to remove the different length of drill pipe (DP) which are still within the BOP and the stack above it.

However, switching to the Enterprise ROV1, suddenly there is a piece of pipe being examined. It is difficult to tell exactly which piece it is, though it is apparently marked in what may be foot intervals, but the examination at the moment is focusing on the end of the pipe, which is the male end of a pipe section, and it is hard to determine whether the threads have been damaged or not. (This is being written as this occurs). MoonofA has an explanation (this was part of the fishing string) and I will add that comment below the fold and the current pictures.

Close-up of the lower end of the pipe

Earlier the pipe had rotated so that an identification number could be seen:


The pipe has a number of spaced marks on it, with five marks higher getting to 70
(suggesting the other side of the joint might have carried a 5).


The mark just below the point where the pipe section goes into the end of the fishing tool that caught it reads 90, and then there are three individual marks and the fishing tool holding the upper end of the pipe section.

Hmm! That’s interesting they have just apparently driven the open end down into the mud:


So that they could release the top and go and look at it.

And it appears, at first, that this was the piece of the pipe that was cut through by the diamond saw that the Admiral referred to in his press briefing.But then they do a close-up of the top and it is the female section of the joint at the other end of the drill pipe.

Upper end of the drill pipe

And this too gets a close examination of the threads.

MoonofA's explanation of this is:
That part of the drill string fell off from one of the two fishing strings the Discoverer Enterprise had brought down. Pretty embarrassing for the crew to lose some 30-60 lower feet of the drillstring with a fishing tool on it only to have to fish for it later on ...

Here is a video by RockyP showing the lost part standing vertically in the mud.

But the Discoverer Enterprise has two derricks and the other derrick had another pipe down with a fishing tool and with a cam inside it. That pipe went down and looked for "fish" inside the stack: Video by Naula.

The first fish found at a depth of 5015 feet was the longer piece of broken drillpipe with a squeezed end and they actually tried successfully to get it inside the overshot tool. But when they yanked the tool up the fish escaped: video in double speed by me.

The camera then went further down and at the height of the flex joint at 5026 feet depth found this:


We are seeing the inside of the flex joint from the camera in the fishing tool. There is in the center-right an open piece of pipe. Next to it is some rough space open where fluids come through from below pumped by the Q-4000 through the choke line of the BOP. At the top of the picture another pipe can be seen which extends above. Both pieces are probably held back by what appear to be hydrates (though this could be just loose "beehives" of hydrates or something else).
Hard hydrates would explains why the first attempt to yank the longer caught fish did not work. It is probably held back by hydrates on its lower end.

The fishing trip has ended for now.

The big question to us at #theoildrum is: How did hydrates form so deep inside of the stack? When was there seawater as well as methane, both needed to form these hydrates, in the BOP and stack at the same time? Or do we see something different than we think?

Heading Out comment - they did remove some of the hydrates using a high-pressure jet earlier in the work, and this should still be down there, so they may go in with a lance to clean out the hydrates, but if they exist throughout the lower BOP then the entire assembly may be frozen in place, and if this extends down into the casing of the well, then as I mentioned in an earlier post, trying to pull up the drill pipe, and even recover the BOP may be halted because they will snap the drill pipe before they will be able to break it loose. Alternately they could try flooding the area with chemicals again.

Earlier in the day Admiral Allen explained some of the events that I discussed in yesterday’s post, noting that the rams in the stack had become jammed because of the formation of hydrates within the mechanism, that then led to them freezing as the hydrates were disturbed. BP then chose to flush the system again, using an antifreeze solution.
Question: What chemicals were used in the recent flush to remove hydrates?

A. BP used a methanol soak as the predominant medium for melting the hydrates. They also circulated MEG water - methyl ethylene glycol (antifreeze) - to help improve visibility conditions.

Q. Will there be ROV feeds available to observe the pipe removal?

A. BP will have the regular suite of ROV's on scene for the operation and the pipe extraction should be visible through the Enterprise ROV camera.
With the problem of the ram movement in the capping stack having been resolved, the plan for the day was to go down inside the stack to recover the pieces of pipe that had been found. One of these is relatively short (about 18-inches long) the second (and here the Admiral corrected a length given earlier) is some 13-ft long, and then there is the section of the DP itself.

Now the segment that appears to have just been removed would be 30-ft long if it were a standard length of DP, so I am wondering if this was a transcription error in the relevant paragraph of the teleconference?

The other issue dealt with by the Admiral dealt with the possibility that when the cement was pumped down the well it might have adhered to part of the drill pipe, and filled a gap between it and the production casing, so that over some unknown interval the DP might be effectively glued to the casing. His comment
We believe we can easily remove two of those pieces of pipe because they're standing free inside lower marine riser package. After that, we will have to determine the condition of the pipe extending down into the blowout preventer, if it goes below that down into the well, if the pipe somehow might have been cut and is suspended there and it was cut below the blowout preventer, there's no pipe we do not know any of that right now because we cannot see down there.

We are creating alternatives that will allow us to either remove the pipe if it's removable. And if it is not, plans to how we were remove the blowout preventer with the pipe attached and bring that to the surface and cut the pipe at some point. Our science team and BP engineers continue to work with all those alternatives as we move forward. We are hoping however to remove the two pieces of pipe and have a better idea today or tomorrow about the remaining piece of pipe.

Unfortunately, not having watched earlier this evening I missed the section of pipe falling off, and what led to the sequence of events i described above, where the two ends of the pipe being examined were, in fact, at one time joined together, rather than being the one section of drill pipe that I had initially thought that they were.

Read more!