Deepwater Oil Spill - BOP on board

First it was hoisted to the surface

Note the actual size of the Deepwater Horizon Blowout Preventer as it is held just above the support frame, after having been raised through the moon pool of the Q4000. Compare the size of the folk standing around. (The BOP is the large frame with the yellow legs on the corners, being held just above the red platform with the four vertical bracing colums).




And then it was lowered and latched into place on the red platform, that can help to move it and support it.

Meanwhile the LMRP that sat above the BOP is still on its way to the surface.



Read more!

Friday, September 3, 2010

Deepwater Oil Spill - changeover completed.

Well, in one day the progress on the Deepwater Horizon moved significantly further towards the end. First the capping stack was removed from the well, and then, after a strong initial tug on the BOP, and transition spool, they were unlatched and moved away by the Q4000. As they left it was clear that there was no pipe, or hydrates under the BOP, though there was a thin film of a liner inside the BOP mount. This was then cleaned off, and a new gasket inserted. Once that was in place, then the new BOP (from the second relief well) was brought to the well, and lowered until it into place. (There is a Youtube video of the separation with the mount and BOP clearly separated by 3 minutes into the tape.)

Waiting for the new BOP

There was no drill pipe under the BOP, when it was lifted, nor any evidence of one or of any hydrates in the casing of the well itself. Thus some of the concerns that I had turned out to be unwarranted, but we did not know until the BOP was gone, what the conditions were likely to be. The next step in the process is to ensure that the BOP is working properly, and then the relief well will be completed at the beginning of next week.

With the "new" BOP in place.

That will likely be when we find out whether the annulus between the production casing and the well liner is full of oil or drilling mud. Given that a number of my concerns over the condition of the well have turned to be worse than the actual condition, I think I will hold off, at this time, on making any on that one.

Read more!

Thursday, September 2, 2010

Deepwater Oil Spill - stack off, but another incident

Once again I am indebted to MoonofA, who is giving a more detailed hour by hour report, of some of the incidents that I miss. Fairly rapidly on Thursday afternoon, the team of ROV’s and surface vessels moved forward with the removal of the existing infrastructure over the Deepwater Horizon well, with the intent of replacing it all with a functioning blowout preventer from the 2nd relief well (which now looks to be no longer necessary at all). One of the first steps was to move the methanol feed (used to dissolve and remove hydrates from the internal structures of the stack) down from the rams of the top stack to feed into the original BOP. This was used to ensure that the different parts of the stack, such as the rams, were able to function, when needed. And now, I presume, the hope is that it will similarly ensure that the BOP rams can function if needed.

Removing the line from the stack


Replacing line on the BOP

Once the feed line had been moved, then the Enterprise came in and lowered the latching device that has been floating just above the stack for the past few days. It did not take long (and by doing so did not convey the difficulty) to drop the cap over the top end of the stack, and not long thereafter the stack was released and lifted away from the underlying transition and the original BOP.

Approaching the stack

The more interesting part of the exercise will come when they start to lift the original BOP and the transition spool. There are a number of different scenarios that have been proposed, depending on what happens, and why, as the first lift begins. If they can lift the BOP with the underlying drill pipe (DP) still attached, then they appear ready to grab hold of the DP after the BOP has risen a short distance, and cut it off. This will make it easier to get the BOP to the surface, and means that a more conventional fishing tool can be used to capture, and bring up the remaining length of the DP. Toolpush, for example, mentions some of the options available.

Sliding into place

The capping stack was released at about 4:30 pm Central, whereupon Admiral Allen issued the following statementz:
"Under the direction of the federal science team and U.S. government engineers, BP has completed the capping stack removal procedure – an important step in the process to remove and preserve the damaged BOP. This procedure was undertaken in accordance with specific conditions I set forth in a directive authorizing the capping stack removal and BOP replacement last week. BP will continue to follow these required conditions for the BOP removal procedure, which is expected to commence this evening. I will continue to provide updates as necessary."
One of the problems with the feeds from the Q4000 is that they are not time-stamped, so that it is hard to know if the latest glance at the feed below the moon pool, which shows that the pipe hasn’t moved since I last looked, is current or not.

The other significant news today was of the fire on the Mariner Energy platform in the Vermillion block of the Gulf of Mexico. The fire now appears out and there was apparently no leakage from the wells that were connected to the platform. The platform is in 340 ft of water, and was fed by 7 wells collectively supplying 1,400 bd of oil and 9.2 mcf of natural gas, that is now shut in.

I note that they were apparently waterblasting the rig and repainting it. One of the things to be careful of in those cases is the static electric charge that can build up in water vapor around the operation. From the Coast Guard report:


However, at this time, that is just conjecture, and we will have to see what the investigation reveals.

Read more!

Wednesday, September 1, 2010

Deepwater Oil Spill - preparing to move

The annotations to the ROV feeds from BP are becoming a little more descriptive, particularly with those related to the Q4000, which will be playing a significant part in the replacement of the blowout preventer (BOP) on the Deepwater Horizon well. However, at 9 pm on the 1st, with the waves still a little higher than desired, the activity has yet to start.

One of the new camera feeds that is being displayed is a weight indicator on the deck of the Q4000. This is not yet on line, but Admiral Allen pointed out on Wednesday the loads that will come onto the vessel.
We anticipate removing the blowout preventer with the latching mechanism that will be attached to a drill pipe string that will be suspended from the Q4000. . . . . . .

The combined weight of the drill string, the latching mechanism and the blowout preventer itself is approximately a million pounds. When they released that blowout preventer from the well it will be suspended at about 5000 feet below the surface.

There are two things we’re concerned about when this occurs, number one is the wave height. You can imagine the Q4000 riding up and down on the waves. When they ride up it exerts more dynamic loading on that pipe system. So we’re concerned about the weight and the ability of the pipe system to handle that.
Before the BOP itself is removed, the capping stack has to be taken off. The latching mechanism to attach to that is already down underwater, and is being monitored by the Enterpise, through ROV2. The stack will come off first, and it is that activity which is now expected to start at noon on Thursday.

Once the Q4000 latches onto the original BOP it is going to raise it up, through the platform of the vessel, and then set it back down on that deck. There are two additional static cameras on the Q4000 which are monitoring the moon pool, and which are presumably going to be carrying all this activity starting tomorrow and running perhaps 36 hours, depending on the weather and how easily the BOP assembly breaks away from the well.

As soon as the Q4000 has the BOP on board, it has to move out of the way (and trans-ship the parts of the BOP, once separated to smaller ships to be sent ashore) so that the new BOP can be put in place.

This is the task for Development Driller 2, but before the job is finished the BOP has to be thoroughly tested to ensure that everything is now functional, the BOP will then be ready for the final stages. At this point it will be possible to restart the relief well to complete the bottom kill. That is still not anticipated to start until after Labor Day.

I am going to insert the quote on what the Admiral said on hydrates it its entirety, since I am not sure exactly what his point was.
Hello, Admiral. Can you tell me how the current BOP is attached to the well head and if there’s any concern about hydrates or other (inaudible) that might make it difficult to latch?

Thad Allen: Well, the current BOP is attached to the wellhead with the same connector they would use for any similar drilling well. To the extent that hydrates are there, we don’t expect that to be a problem right now. Had we continued to try and fish and get the pipe out of there, there was some concerns that hydrates would be blocking our ability to use a camera and actually operate down there. So I’m not sure that’s an issue. If there’s an issue at all, it’s probably the issue of the condition of the wellhead itself. When the Deepwater Horizon exploded and sank it bent the riser pipe over and ultimately the riser pipe was severed from the drill rig. At that point, if you can imagine, as massive as the blowout preventer was and that wellhead was, it probably bent over to some extent and then when the riser pipe separated from the rig it popped back up. It did not pop straight back up and there’s been some attempt to level that, to make sure we could get that as close to vertical as we can. I believe the current estimate right now, it is about two degrees off center line. So as we go in to pull the blow out preventer out, I would say hydrates are not a real big concern. I think the alignment to the true vertical about two degrees off would impact somehow to a very small degree the pull on the BOP as you’re trying to free it. We are aware of it. The engineers have taken that into account. We don’t think it will be a prohibiting condition, but it is something we are aware of.



In the other story that I have been watching, that of the miners in Chile, the equipment has started, and the preliminary drilling of the central shaft is now down more that 20 m. At the same time the rescuers are considering ways of reaming one of the smaller drill holes that have already reached the area. This might take a greater number of stages to get the hole out to the required size, but could, in total, be faster than the two-stage operation that is currently in progress. In either case moving the muck from the bottom of the excavation with wheelbarrows, and ensuring that none of it gets stuck as it falls from the machine, are both concerns that will have to be addressed as the work moves forward.

Read more!

Monday, August 30, 2010

Deepwater Oil Spill - another weather pause

The weather is currently holding up the proceedings at the Deepwater Horizon well site. The seas are some six to eight feet, which is apparently the height of the top 1/3 of all waves. (There is a table that shows how it is affected by wind speed, duration and fetch, which last is the surface area that is being affected by that wind). There is a site with a post on wind basics that explains). So the underwater effort is likely to be put off for another two to three days (depending on how Earl behaves, though it's not supposed to get close, but it might. The current problems are more local to the Mississippi Delta). So there will be a delay for at least a couple of days until the water settles down a little more. The problem is caused by the considerable length of the risers and cables on which the large steel structures sitting at the sea bed will ride as they are moved about. With the waves lifting and the swells rocking the vessels there are risks both from the changes in dynamic loading, and also in generating a pendulum effect as the weights sway. Much better to pause a little longer.
At his press conference today the Admiral described the plans for the next step in the process:
the Discoverer Enterprise (will) remove the capping stack and then back off. (At) that point (the) Q4000 will come in and lift the blowout preventer (BOP) which will also (hold) the transition spool which was put in to accommodate the capping stack. And a third step will be (for the) Development Driller II, which is drilling a second relief well, (and which) will move in with the new blowout preventer, and put the blowout preventer on.

Once that blowout preventer is in place, the well will be in a position to withstand the pressures expected on the intercepts of the analysts by Development Driller III and the drilling mud that will be forced in there when that happens. All is in readiness, and at this point we are just standing by for a weather window.
In discussing the current thoughts on why there are three pieces of pipe in the BOP, the Admiral also explained where his concept of the the pipe being fragile was generated.
When we first were looking at the riser pipe, if you remember, there was a kink. And then we were looking to cut the riser pipe, and we made a shear cut. And then we actually unbolted the stub that was bolted to the flanges before we put the capping stack on. At one point, we actually saw two pieces of pipe.

The original presumption at that point, and this is a long time ago now, was that a part of the pipe had fallen down into the Lower Marine Riser Package, and it was alongside a pipe that was extending through the centerline down into the BOP. As we have gotten into the blowout preventer itself and taken a good look at it, we found out that that pipe is fragile, is broken into three pieces, and we no longer have a pipe that's suspended in the centerline.

So our assumption is, our original assumptions on the pipe – and at that time they actually might have been. These pipes are being subjected to a lot of different forces in there. If you remember, we've had the dynamic kill and the static kill. There have been a lot of different fluids that have been forced through the blowout preventer or the capping stack, Lower Marine Riser Package.

In general, we have concluded that the pipe is of extreme fragility. And while we could try and recover it, the pipe that we can get to right now is not connected to any pipe that is on the (center) line. It could extend out into the BOP. So for that reason we just foregone any more fishing experiments, and have gone directly to remove the blowout preventer.
If I understand this correctly the current thinking is that none of the pieces of pipe above the shear ram are being held by it, and that they are less consequential as a result. Whether that also means that the DP was actually sheared in half by the ram is a different question, but apparently not one that the current investigation is going to look at further at the moment.

It does, peripherally suggest that there may not be any pipe now below the rams. Because if the different treatments that have caused the pipe to break into these bits did so across the shear ram plane, then there may not be enough holding the pipe below the BOP and it may be long gone. The gamma scan that showed the DP was there was, after all taken very early in this process, and much has happened to the well since.

The Admiral also noted that the drop in pressure (from the anticipated perhaps 9,000 psi) when the well was finally shut in is now believed to be due to reservoir depletion.

Oh, and for those of you admiring the ability of those on the platform to fish, the Admiral noted that the team involved in those operations included BP, Schlumberger, Transocean, Cameron and Baker Hughes personnel.

Incidentally I also think there was another transcription error (I tried to smooth some earlier ones by interpreting the words transcribed with my own (in paren, within the quotes). In dealing with the question of whether the DP is still there, and if it is held in place with either hydrates or cement he said:
The answer is I don't think we know. You know we think there may be a chance the pipe might have adhered to cement during the static kill process. We don't know that to a virtual certainty. But we don't want to try and pull the blowout preventer without having a contingency ready to deal with that eventuality.

So what we're doing is, we're going to life the blowout preventer. If it doesn't come off easily, we’re going to apply 80,000 pounds of lift. And maybe somewhat of a mis—we'll calling that the gentle pull. If for some reason that does not free the pipe then we will go in and mechanically open the rams and lift the blowout preventer out over the pipe, and then we'll share the pipe with the wellhead.
I believe that last ‘share” should be “shear” and will, actually, more likely be a saw cut.

And the small flow of bubbles from the stack, which the Admiral feels inconsequential, as earlier such flows proved to be, is still going on.



Read more!

Tuesday, July 13, 2010

Deepwater Oil Spill - awaiting the integrity test

Ah! The joys of trying to work out what is happening at the seabed around the leaking well in the Gulf, and relying on the images from the ROV cameras. Consider the image that I have just pulled up from the Enterprise ROV 1, which BP has designated as “looking for leaks.” Not wishing to be querulous but that looks suspiciously like a diamond cutting saw in the ROV’s clasp.

Image from the Enterprise ROV 1 – “performing leak monitoring.”

On that little note of caution, there does seem to be some delay, or perhaps “slow, methodical, unseen progress” in regard to closing the valves etc in order to test the integrity of the well. At roughly 10 pm Eastern, the flow does not appear to have changed much, if at all, and the BP site notes that the test has not yet started. (Nor has it two hours later having finished writing this post).

The white pipe is injecting dispersant, that changes the color of the oil/gas to more brown and seems to be coming in spurts rather than regularly at the moment, but this may be because of the changes in the equipment below the leak, which is likely siphoning off a considerable volume from the well.

I do note, however that Secretary Chu came down to monitor the test today, and this may have a little impact on the schedules.

His involvement in the spill has been continually underlined by the Administration.
Secretary Chu assembled a scientific team of top scientists and has made three trips to Houston, monitoring the progress of BP's effort to contain the leak and helping to design the strategies for moving forward. The team includes:

Dr. Tom Hunter, Director of the Department of Energy's Sandia National Laboratories
Dr. George A. Cooper, an expert in materials science and retired professor from UC Berkeley
Richard Lawrence Garwin, a physicist and IBM Fellow Emeritus
Dr. Alexander H. Slocum, professor of mechanical engineering at MIT

(Ed. note - George Cooper, who I know and respect, is a retired petroleum engineer)

Secretary Chu is on the phone with his science team a minimum of 1-2 times a day, 7 days a week, and the calls frequently last 90 minutes or more. Secretary Chu and members of his team also have a dialogue with BP executives each morning.
They visited the BOP manufacturer (Cameron) and their main competitor (National Oilwell Varco) back in May, and have had, among other things, the following input to the operation:
• Due to our suggestion, BP used high energy gamma rays to image parts of the internal state of the BOP. Lab personnel have independently analyzed the 2D gamma ray images. That imaging is crucial in helping understand what is happening inside the BOP and informing the approach moving forward. For example, it told engineers which valves and rams inside the BOP were closed and which were open, and it showed that a piece of drill pipe was stuck inside the BOP. Trying to determine what was wrong with the BOP without this information is akin to determining why your car has stopped running if you have no working gauges and can't open the hood.
• They strongly encouraged BP to collect additional pressure measurements, which were very valuable in interpreting the behavior of the well and BOP after each top kill and/or junk shot attempt, and ultimately those measurements helped the government and BP determine that the top kill was not going to work and that it was time to move on. The measurements also showed that the top kill attempts did not significantly erode the BOP.
• During the top kill attempts, the team suggested rechecking all of the hydraulics on the BOP, which BP did. As a result, one of the pipe ram valves closed more tightly and provided more resistance to the flow.
• The team conducted an extensive suite of structural analyses to assess the stability of the riser system in support of the choke and kill series.
• The team conducted an independent set of analyses to explain the oil and mud flow during the choke and kill series. This provided an understanding of the operational limits of the containment system going forward.
The list does not, however, appear to have been updated since June 15th.

After the visit today Admiral Allen issued the following statement:
"Today I met with Secretary Chu, Marcia McNutt and other scientists and geologists as well as officials from BP and other industry representatives as we continue to prepare and review protocols for the well integrity test - including the seismic mapping run that was made around the well site this morning. As a result of these discussions, we decided that the process may benefit from additional analysis that will be performed tonight and tomorrow.

Both the Helix Producer and the Q4000 collection systems are currently on line with the potential to exceed the containment capability that existed before the sealing cap was installed, and skimmers continue to be surged to the well site in anticipation of any increased oil flow as part of the transition. The drilling of relief wells also continues- the first relief has been drilled to a depth of 17,840 feet below the Gulf surface, and the second to a depth of approximately 15,963 feet below the surface."
The time of the more than 200 scientists and engineers that the Secretary has involved in these decisions is no doubt a part of the $99.7 million bill that the Administration presented to BP today. BP have already paid previous bills totaling $122.3 million to the Administration.

In today’s briefing the Admiral noted that the seismic run that was carried out this morning was to provide a baseline measurement of the seabed condition before the pressurization test of the well casing occurred. It also had to be carried out in daylight, since the vessel running the sensors had to steam through the fleet assembled around the well, and the sensors also were likely to be degraded by too much adjacent noise as they ran the scan.

He also corrected the sequence for the close down of the flows out of the well. (My concern yesterday) The sequence is
When we get ready to start the well integrity test, we will first cease production through the Q4000 and the Helix Producer I. We will then divert all the hydrocarbons up into the new capping stack. Valves through the kill and the choke lines for the new capping stack will be opened. And the center bore is already open. So we will be venting basically through three different exits on the capping stack, the kill line and the choke line, and the main line going through the bore.

Then in sequence we will attempt to close the stack down and assess the pressure readings. As we do that, the first thing we will do is close the main ram. There are three rams. The middle one will be closed and that will basically shut off the flow outward through the top of the capping stack. At that point we’ll take pressure readings. We will then close the kill line, which is the second remaining outlet and take pressure readings.

The third and most critical will be the choke line. There is a special device that has been built on the capping stack. You will see it. If you look at the video, it is yellow. It is long horizontally and it is a curved up pipe for the exit of the hydrocarbons. That choke line will be controlled by a remotely operating vehicle, which will slowly close it incrementally. And this is going to be very, very important because we want to measure the amount of closure, which will be measured gradually by turns of that choke line valve by an ROV simultaneously taking pressure readings.

The goal is to slowly close that down and understand the changes in pressure as we are closing it until that choke line is closed. At that point, there’ll be no hydrocarbons exiting from the capping stack. And we will go into a period where we’re going to start taking pressure readings. It will go in basically 6, 24, and 48 hour increments depending on the results.
Once the well is shut in then the pressure at the BOP (which is monitored by transducers and not the visible gages) should rise to between 8 and 9,000 psi (which Admiral Allen, a long time ago, had said was monitored just downstream of the BOP at the start of remediation). This is the anticipated value when the weight of the oil/gas column is subtracted from the pressure in the bottom of the well. Anything less than this will indicate that there may be some problems within the body of the well. Incidentally the gages that the ROVs are monitoring are monitoring pressures in the accumulator lines that run the hydraulics of the rams and power tools.

The Admiral was also more precise on the exact location of the relief well
Development Driller III is now at 17,840 feet measured depth. They’ve been there for a day or two. They are doing testing to make sure they have the right angle of attack as they close in for the last 60 or 70 feet before they’ll actually try and make the penetration for the relief well.

And the current estimate of how far away they are from the condo well at this point is four feet four inches. So you can imagine this gets pretty precise as they’re trying to go down another 60 or so feet and actually hit the point where they can drill into the annulus and potentially to a seven inch casing pipe. So that continues as well.
The Admiral noted that they are on pace to have 1,000 skimmers along the coast by the end of the month, and that they are using 2 million tyvek suits a month (the suits worn in cleaning the beaches) and there is a growing concern about the national supply of these.

And he pointed out that a part of the shut-down process will be visible
What we will do in sequence is we will stop production on the Q4000 and the Helix Producer I and remove the way for the hydrocarbons to exit through the kill and the choke lines on the original blow out preventer. That will move to three exit points, the choke and the kill lines of the capping stack and then the top opening of the capping stack. Then we will in sequence first, there are three rams that are a part of the capping stack. The middle ram will be closed. That will seal the upper opening from any hydrocarbon release. That will leave us the kill and the choke lines.

The kill line will then be closed as well. Now remember this is either open or shut. That will leave the choke line of the capping stack as a last way for hydrocarbons to exit from the capping stack. And that is set up with a specially designed engineered and built, you’ll be able to see it on the video. It’s a horizontal, yellow piece of equipment that has a pipe that curves up where the hydrocarbons would exit and at the other end there’s a place to insert a tool with a remotely operated vehicle and then slowly close the valve, which we will do that while we are taking pressure readings.
This is the control panel he was talking about, taken at 5 pm Eastern.


BP is also now holding twice daily briefings. In the morning one Kent Wells gave the actual timeline for the 3-ram stack installation
First in terms of the capping stack, last night at 6:20 pm we actually landed the stack on top of the transition spool. By 7:00 we had it fully connected and sealed on top of that device. And then at 8:30 we actually disconnected the drill pipe from the drill ship enterprise from it and so it was in place and free standing at that point in time.
The tests of the flow to the Helix Producer showed that it could sustain flows of up to 12,500 bd (as high as they went) He slightly corrected the Admiral on the relief well:
The first relief well is at 17,840 feet. Right now we’re running another survey to confirm the distance from the Macondo well, the direction from the Macondo well and the inclination of it.

We only have another 30 feet to drill before our final casing point and so we want to make sure that this well is perfectly lined up. So that’s why we’re doing this confirmation run. We’ll do that then we’ll trip back in the hole and we’ll drill that final 30 feet. Then we’ll come back in and what we call open up the hole to make it large enough to run the casing and most likely we’ll be running casing in the hall on Sunday, but of course there can be variability to that. But what I would say is that we’re on track and I’m still looking for the most likely intercept of the Macondo well being at the end of July.
He went on to say, in regard to that intersection
So the inclination we’re looking for at the bottom is somewhere in the range of two to two and a half degrees and we think we’re in that range, we just want to confirm that. And that lines us up as we then – after we set the casing I’ll come back and talk about that in a second. We’ll have about 100 to 150, 200 feet to drill to intersect and that two degree angle allows us to do that in that period of time. So that’s why we want that particular angle.

In the afternoon briefing he pointed out that when the sequence of tests on the 3-ram stack begins:
down below two rams there’s a what we call our flow T and there’s two sides to it and that’s where the flow would be coming out when we actually shut one of the rams.
However, as I pointed out at the start of this post (and as still holds true) the integrity test has yet to be initiated.

Read more!

Monday, July 12, 2010

Deepwater Oil Spill - the 3-ram stack

After a relatively long and technically difficult process BP has managed to locate and install the three-ram Lower Stack on the flowing well in the Gulf. At the same time the viewing site has been changed, so that the feeds from all 14 ROVs can be seen together. The view from Skandi ROV2 shows the flow from the well is now issuing from the segment of drill pipe left at the top of the stack, after the installing drill pipe was disconnected.

Flow from the top of the 3-ram stack at 10:45 pm Eastern Monday – the color is due to the injection (through the white feed) of the dispersant into the flow.

Just as a reminder, this is how the assembly looks underneath this drill pipe.



The White cylinder above the yellow transition spool is designated by Cameron (who make it) as a Cameron HC 18¾-in., 10000 psi connector, with the HC designation standing for High Capacity. Inside it looks like this:



BP held a press conference on Monday in which they commented on the problems noted on Sunday with the Helix Producer feed, and that these had been fixed.
We did encounter two problems which created some delay yesterday. One was with issues on a hydraulic control line for a valve (so that it couldn’t work) and the second was a leak in the methanol system. Both of those issues have been resolved and we will be starting up the helix producer later today. It will likely take several days to ramp up to a full capacity, which is at about 25,000 barrels a day, which with the Q4000 would give us a total capacity of around 33,000 barrels a day of containment.
BP also admitted to a slight problem that delayed the installation of the 3-ram stack today, though as with the flow line problem it has also been fixed to allow the installation which was completed after the press conference.
We did have a problem with the deployment real (sic) on the Inspiration. We had a backup plan and moved to that backup plan and will be attaching the cap later this morning.
With the stack in position, the next step is to connect up the hydraulics, so that the power can be applied to the rams and that they will close the flow. This is some of what is going on with the array of other ROVs whose operations are now available for monitoring.

Prior to that I suspect that they will, Monday evening, check the flow of oil through the kill line to the Helix Producer, to ensure that it can handle the flow, and that this will occur concurrent with the flow to the Q4000. Once those numbers have been confirmed, and the flow conditions validated, the shear rams will be closed. I would suspect that this will happen first, since it will increase the pressure in the well somewhat, as the flow path out is restricted to the kill and choke circuits. Then, after checking to ensure that the well is retaining its integrity – no leaks into the surrounding rock through the casing or any other of the horrific disasters that have floated through comments over the past few weeks – the flow to the choke and kill will slowly be closed. As they are closed the pressure in the well will continue to be monitored, together with the flow out of the two lines. (Having now read the full transcript I note that BP are going to do it the other way around, closing the rams last instead of first. Well I think it might be more logical to do it the other way, but they know more about the relative benefits of the choice than I).

If the pressure continues to rise (indicating no leaks) as the flow trails to zero, then the well will have been shut-in. The flow will have stopped, and a test will be run, for a planned 48 hours to ensure that all the seals are holding.

At that time I expect that the choke and kill lines may re-open, but without there being some unforeseen incident, I do not expect the rams to re-open. Once the well stops pumping out oil into the Gulf, the political difficulties in restarting that flow un-necessarily are considerable. And if there is a problem then in addition to the choke and kill lines the riser to the Enterprise can be re-connected, and take 15,000 bd up the pipe, for a total system capacity of around 50,000 bd without letting any more oil out into the water.

If the current tests are successful, then the risks of additional leakage into the Gulf during a Hurricane are also going to be greatly reduced, and the pressure on the relief well becomes a little less.
We’re now at 17,840 feet. We’ve completed our eleventh ranging run to locate the original well bore, we’re approximately five feet away from that well and we’re about 30 feet vertically from the point at which we’ll set casing. We expect the casing operation to begin this coming weekend.
Work on the second relief well has now been stopped with the current end cased and cemented, until circumstances indicate that it will be needed.

The process to cement the last casing was also reviewed
we’ll get to the final casing point. Then we actually do what we call open up the hole. We just make the hole a little larger so that we can run the casing an cement it in place. After we do that we’ll run some logs, which are basically tell us about the cement bond log, tell us about making sure everything’s right. And then we’ll prepare to start to drill out and we’ll have done a BOP test before doing, so there's a fair amount of work to do before we sort of start to drill out.

And then we’ve got about another hundred feet to go, is what we’re anticipating before we intersect the Macondo well, and of course that will be plus or minus, it won't be exactly a hundred feet. But it will be in that range. But we would drill that very precisely doing a number of ranging runs. And that will all take time so that’s why you’ve heard me talk before. I anticipateus intercepting the Macondo well sometimes toward the end of July and then the kill procedure, the kill and cementing procedure, depending upon where the flow is, analysis, casing or boat, could be anywhere from a number of days to a few weeks to do that.
Incidentally in the press conference on Sunday morning Kent Wells noted that each of the bolts on the flange of the riser weighed 52 lbs.

In the afternoon briefing they also noted that there was only one piece of drill pipe found in the BOP, at the moment no-one knows what happened to the second piece of pipe.

And for those who, like me, have some difficulty working out which camera is showing what, here are some additional shots of the stack (h/t Mark Moore), from different angles, so that some of the component locations may be clearer.


And this is the main control panel, with the ability to operate the valves with the ROVs made rather evident. I suspect this picture was taken a little while ago, and the port cut for a valve with a cutting torch has been cleaned up a little since then.



Read more!

Sunday, July 11, 2010

Deepwater Oil Spill - inserting the transition spool

At about 1 pm (Eastern) I checked on the feeds, and it appears, using the camera on the BOA ROV 1, that the transition spool has been lowered into place (the old riser was removed at about 3 am this morning) and is now ready to be inserted into the top of the riser.

Flange removed from the well, and the surface awaits the transition spool.

Transition spool approaches the flowing well

I will update as I notice other things of interest - though will be out some of this afternoon.

UPDATE 1. Apparently there was some soccer game or something on this afternoon, so I became a bit distracted, and was not watching when the transition spool was seated, some time around 3 pm. Since then they have been tightening the bolts. The next step will be to set the Lower stack on top of the spool, and then lock it in place.

UPDATE 2. The Ocean Intervention ROV 1 keeps looking at a pressure gage as it manipulates around the transition spool.

Pressure gage (which goes up to a pressure of 6,500 to 7,000 psi)

I suspect that this is the pressure in the hydraulics when they do the final tightening of the bolts on the transition spool, to ensure that they are adequately all tightened, since, after looking at the gage, it went over and moved the torque wrench to another bolt.

Torque wrench being moved around the bolts holding the transition spool in place on the BOP.

Obviously assembling the rig is taking a bit longer than I thought, though I think I may have seen the Lower capping stack somewhere around in an earlier shot.

Looking at the various camera shots on Monday morning, there are a lot of pictures of gages around the kill line that would be feeding oil down the new line from the BOP. Given that they are all still reading zero, it suggests that there is a little problem.

Also the word is apparently out that the capping stack is on its way down to the site.

Ane here it is, being monitored by the Inspiration ROV, which you see through the the Akamai video set .

Read more!

Saturday, July 10, 2010

Deepwater Oil Spill - starting to change the cap

This weekend BP are carrying out two steps that will move the process of reducing the oil flow, and killing the well further forward. In fact, should the new sealing cap be placed over the well by Monday, then, with the new connections that are then to be made, there may well be no more oil flowing into the Gulf from shortly after that new collection system becomes fully effective.

There are two parts to the process. The more immediate part, that would have been in place, except for the bad weather, is the connecting of the flow from the kill ports on the BOP to the floating riser and the Helix Producer. At the same time the old riser section is being removed from the top of the well. At the moment (9:15 pm Saturday evening) the ROVs from the Ocean Intervention are working on continuing to loosen the bolts on the riser flange. The box to the left has just been brought to the riser by Ocean Intervention ROV2, and this view is from ROV1. (Skandi ROV1 also appears to be monitoring the operation).



The view from ROV1 also shows, intermittently, one of the two pipe segments inside the riser.


Kent Wells has described the process that is being carried out, noting that as the testing of the new cap proceeds, once it is installed, it might be possible to shut the well in.

The flex joint has been straightened and blocked into place, and is aligned with the BOP. And the cap itself is a much more complex structure than had originally been discussed. It will also be installed in a number of stages, and I will use Kent Wells illustrations and comments to walk through this.

The first step, in the installation process was the alignment of the flex joint and the removal of the old cap. The second (currently ongoing) is the unbolting of the old flange. There are 6 bolts to be removed, shown in this illustration as well as above:


There are a couple of tools that have been developed to split the two halves of the flange after the bolts have been removed – the initial one will be fielded from the Inspiration drillship, and will fit around the flange, so that the top segment can be just lifted off.


This will expose the two segments of drill pipe that are sticking out of the BOP, and so these will then be strapped together, so that they will fit within the transition spool. A guide shoe and positioning pins will be used to help lower this in place, and then the ROVs will bolt the 12 ft flange transition spool (the yellow segment) to the top of the old BOP.




The 18-ft Lower Capping stack will now be lowered, on drill pipe, to fit on top of the transition spool. It sits on the HC connector, and is fitted with rams to control or stop the flow, and connectors that will allow feed of the oil to the different risers that will carry it from the well to the surface vessels.

The capping stack has a perforated pipe at the top, and initially oil and gas will issue from that pipe, once the stack is locked in place.


At the moment there is some doubt as to whether the fixtures on the top of the well, and the well itself, can hold pressure. In other words if they seal off the well, will the internal pressure rupture one of the casings or the BOP. With the capping stack, with its control rams in place, the well can be gradually shut-in, while pressure and strains in the system are monitored. The flows can possibly be reduced, diverted to the surface vessels, or even, if the results are favorable, even completely shut down.

There is an animation of the process, that was put together to allow the teams who will be doing this, to be trained in the assembly of the system. BP currently projects that it is going to take 4 – 7 days.

And at the moment the Ocean Intervention ROV2 is cleaning off the side of the flange, so that the joint can be seen. (The wire brush is rotating so you can’t see the strands).


And at this stage, it looks as though they have the bolts loosened - vide the one above the brush, and these below, which appear partly backed out and thus we may already be waiting for the separation tool to come down and remove the old riser. Then the transition spool (under the BOA ROV control) will be moved into place.


We will wait and see how this unfolds as the day progresses.

Read more!

Deepwater Oil Spill - the end game plan

At roughly 9 pm on Friday evening, Admiral Allen approved BP’s plan for replacing the cap on the Deepwater horizon well, and proceeding with the intersection of the well itself.

That plan includes two things of interest. The first is the schedule itself, while the second correlates the measured depths (MD) with the true vertical depths (TVD) so that the different illustrations that I have used in the past, and the Admiral’s briefing numbers can now be correlated. Note that the lower sections of both wells are shown with rough walls indicating that the wells are not lined over those intervals, and that the walls of the hole are relatively rough rock - albeit perhaps not as rough as the scale might imply.



The BP letter shows that the final casing run has yet to be made, and that this is scheduled to take 8 days.

The schedule for the replacement of the cap is anticipated to take 5 – 9 days, depending on how the job flows and what contingencies have to be implemented.




Read more!