Showing posts with label well integrity. Show all posts
Showing posts with label well integrity. Show all posts

Tuesday, August 10, 2010

Deepwater Oil Spill - relief well intersection version 2

Both Admiral Allen and Kent Wells (audio only no transcript yet) held press conferences today. The primary focus in both cases was the weather, with the currently approaching storm producing waves that are causing a halt to operations.

Gathering potential storms (National Hurricane Center)

The storm is not seen as being very threatening, to the point that the riser will not be disconnected. However the drill pipe is being withdrawn, a storm packer inserted into the hole, and the riser filled with sea water. As a result, if there is a problem, the drilling rig can release from the well without creating further complications. But it allows a faster recovery if nothing untoward happens.

The relief well had made it 50 ft beyond the casing and has been surveyed. In the next step it will go another 30 ft before a survey, and then (getting closer to the original well) another 15 ft and so forth. At any time it may intersect the well, and so it might be appropriate to explain (as both parties did) what is expected, and where the intersection can occur.

When I had earlier written about the intersection and the injection of the cement into the bottom of the well it was before the well had been killed from the top. The situation at the moment is that the bottom 5,000 ft of the well inside the casing has been filled with cement.

So that if I go back to the original situation at the intended intersection point, what it may well look like at the moment is this:


The vertical gap between the two outer cement linings which (for simplicity) I have shown as very short is actually likely to be a couple of hundred feet long perhaps. The inner cement plug within the production casing stretches several thousand feet above the intersection point.

The bottom of the well is some 800 feet further down the production casing. At the present time the well is being held at 4,200 psi pressure at the BOP to check and see if there are any leaks. Just as an observation when you put that much pressure on that long a solid confined column it will dissipate out to side loading long before it gets down to this depth, so the test does not have that much value in these particular circumstances. As far as testing the integrity of the central concrete plug neither will the negative pressure test which they intend to follow the current positive pressure test with. In this case they will lower the pressure in the well to 2,300 to 3,000 psi, and see if the well makes fluid. Again, because of the length of the concrete column in the production casing, that drop in pressure will not extend down to the intersection point (let alone the bottom of the well) and thus won’t provide that much information on the conditions at the reservoir.

What it will do, however, is provide some information about what might be going on in the annulus and particularly what might be in the gap, and the condition of it before the relief well runs into it. If the integrity of the production casing remains, (except potentially at the bottom of the well) and all the mud and cement flowed down it, and into the formation, then there may be no way for the fluids in this annulus to have escaped the well. (I have colored them an off yellow since we don’t know if they are oil or mud). If they are the original drilling mud, and the lower cement lining around the production casing has retained enough integrity to seal this zone off from the bottom of the well and the reservoir, then this may even still be the mud used just prior to the cementing of the production casing.

In that case the well is really already well sealed, although for insurance they will likely pump cement into the well to fill the gap and back up the annulus a few hundred feet with more cement. Doesn’t matter then what the condition of the bottom of the well is – there is no path for fluid to get up the well.

If on the other hand they find some oil in the gap then this could indicate that the cement had lost some integrity, and allowed some oil passage (but then how did it then get into the solid steel pipe of the production casing?) But again, pumping cement into the well to fill the gap will provide a permanent seal without needing to go much distance down into the lower cement lining to assess its condition.

Because the original well could well now be a sealed system then the actual fluid in this section will be determined by looking at what comes back up out of the relief well as it drills into the gap.

There is a caveat to this, however. If there was a massive failure of the lower cement liner down to the reservoir, then when the relief well strikes the gap there will be a path for mud to flow down into the well, pushing the fluid before it down into the reservoir. The mud weight that they are using is a 13.8 ppg mud, and so this should displace down to the reservoir. By monitoring the flow and the pressure it will be possible then to determine the size of the flow channel, and other values. If that happens it might complicate the analysis of what actually is the condition of the bottom of the original well. But the treatment remains the same. Stabilize the well, then inject the cement to form a plug in the gap and back up the annulus, and the well is sealed.

Because of the currently anticipated storm it is expected that there will be a delay of perhaps a few days more before the intersection occurs, but with the condition of the rock around the well in the unsupported (unlined) section somewhat unknown it is not going to be possible to accurately predict exactly when that intersection will occur.

Read more!

Monday, July 19, 2010

Deepwater Oil Spill - bubble, bubble oil and trouble

UPDATE on this post. Although there has been some additional discussion, and the test has been allowed to run another 24-hours, not much else has changed over the past 24 hours, apart from knowing that the anomaly on the BOP is a slight leak on the flexible joint. I am going, therefore, just to add to the earlier post, to give an update on the overall situation.

I rather suspect that we will know a lot more about the behavior of the sediments and matter at the bottom of the Gulf within the next year or so than we have learned in the past hundred years. I am looking at the view from the Skandi ROV 2 at 10 am on Monday, and it is looking at a patch of mud that is bubbling a little, though over a relatively significant area (that of the camera illumination). There is no trace of oil venting and flowing upwards (and a fish just swam by) so there will be, no doubt, some samples taken, and, over time, we will learn what is the cause.



There were other views, from different ROVs that seemed to show clouds of something, but the definition was poor and it was not clear that this was not mud that the ROV itself has stirred up. This has been the case several times today, in watching the video, though there were, in the seep area, shots of small drops of oil heading up to the sea surface.

Given the debate that is developing between BP and the panel that advises Secretary Chu and Admiral Allen, the redirection of the thought process to include another attempt at a top kill, brings in a whole pile of new matter to be used in those discussions

As the day continued there has been clarification of the remarks that both Admiral Allen and Kent Wells have made in the past, as well as an update on the relief well progress, and the resurrection of the idea of possibly doing a top kill. Looking at the Kent Wells conference at 5 pm he began by reporting on the status of the relief well:
Our first relief well, the total depth is at 17862, that’s our casing point. We’re four feet horizontally from the Macondo well at 2.8 degrees and we’re looking directly at the Macondo well. So we’re absolutely perfectly positioned. The team is feeling very good about how they’ve set this well up.

They’re now in the process of what we call opening the hole. So they’re drilling the hole a little bit bigger diameter and then on Wednesday, Thursday we’ll run casing and cement is in place and there’s some testing to do followed by the drill out and ranging runs

The pressure in the well itself has rise to over 6810 psi and is rising at about 1 psi per hour. This lower pressure than the pressures originally estimated makes it possible to reconsider the top kill option. This is where, by feeding mud into the top of the well through the kill line, while the well is shut-in, the mud fills up the well. (The oil and gas are pushed back into the formation). Then should they be able to fill the well up with this mud, the weight of the full column of it, down the well, would be high enough to balance the pressure of the oil in the formation. At this point, rather than the well being shut in, by the cap, it becomes killed by the mud pressure on the flow. There is no longer any concern about pumping the mud in at any high rate of pressure, since the flow is already stopped. Instead the mud flow and pressure can be set to a slightly higher pressure than currently is in the well, and then slowly increase the flow to fill the well, without bringing the pressure to such a high level as to further compromise the well integrity. The injection would be followed with cement, to seal the well at the top of the underground part. This would later be followed by the well intersection by the relief well, and an injection of cement at the bottom of the well.

There are three areas where concern has been raised over the possibility of oil escaping the well below the sea bed and migrating back up to the surface. This is why the ROVs are located around the well monitoring the sea bed itself. There are, as noted earlier, patches where the sea bed is evidently bubbling (in that you can see where the bubbles pop out of the mud). But there is no sign of gas or oil then slowly rising to the sea surface from the bubble action. It may, therefore be something like a field of clams sitting below the surface and aspirating and then spitting out some of the sea water. This action is not at the moment of concern, BP has checked the fluid coming out of the sediment and it is running at around 15% methane, which could just arise (according to Mr Wells) from biodegradation in the mud below the sea bed.

There is a natural seep some 3 miles from the site, this hydrocarbon flow has been tested and is not related to the Deepwater Spill. And so the only other area of concern is a very small leak coming out from the seal in the flexible joint (which, if you remember was straightened before the new cap was installed). The leak, at the moment is very small, and not of that much concern. However if the leak starts to get bigger, and then turn into a stream, it may pick up some of the sand that is reported as being a concern from being in the BOP assembly. This will then, at the pressures anticipated, be enough to erode out the leak to an unacceptable size within a couple of hours. For now, however, it is very small, and not continuous flow, and so can be viewed with less concern, relative to other issues.
The leak was detected in a flange between the top of the well and the rams that regulate flow up the main bore.

Video footage is showing some hydrate build up on the outside of the stack and scientists believe a small amount of oil and natural gas is leaking out.

Allen said the leak is not expected to hurt performance of the device and is not seen as a threat to its structural integrity.



Read more!

Tuesday, July 13, 2010

Deepwater Oil Spill - awaiting the integrity test

Ah! The joys of trying to work out what is happening at the seabed around the leaking well in the Gulf, and relying on the images from the ROV cameras. Consider the image that I have just pulled up from the Enterprise ROV 1, which BP has designated as “looking for leaks.” Not wishing to be querulous but that looks suspiciously like a diamond cutting saw in the ROV’s clasp.

Image from the Enterprise ROV 1 – “performing leak monitoring.”

On that little note of caution, there does seem to be some delay, or perhaps “slow, methodical, unseen progress” in regard to closing the valves etc in order to test the integrity of the well. At roughly 10 pm Eastern, the flow does not appear to have changed much, if at all, and the BP site notes that the test has not yet started. (Nor has it two hours later having finished writing this post).

The white pipe is injecting dispersant, that changes the color of the oil/gas to more brown and seems to be coming in spurts rather than regularly at the moment, but this may be because of the changes in the equipment below the leak, which is likely siphoning off a considerable volume from the well.

I do note, however that Secretary Chu came down to monitor the test today, and this may have a little impact on the schedules.

His involvement in the spill has been continually underlined by the Administration.
Secretary Chu assembled a scientific team of top scientists and has made three trips to Houston, monitoring the progress of BP's effort to contain the leak and helping to design the strategies for moving forward. The team includes:

Dr. Tom Hunter, Director of the Department of Energy's Sandia National Laboratories
Dr. George A. Cooper, an expert in materials science and retired professor from UC Berkeley
Richard Lawrence Garwin, a physicist and IBM Fellow Emeritus
Dr. Alexander H. Slocum, professor of mechanical engineering at MIT

(Ed. note - George Cooper, who I know and respect, is a retired petroleum engineer)

Secretary Chu is on the phone with his science team a minimum of 1-2 times a day, 7 days a week, and the calls frequently last 90 minutes or more. Secretary Chu and members of his team also have a dialogue with BP executives each morning.
They visited the BOP manufacturer (Cameron) and their main competitor (National Oilwell Varco) back in May, and have had, among other things, the following input to the operation:
• Due to our suggestion, BP used high energy gamma rays to image parts of the internal state of the BOP. Lab personnel have independently analyzed the 2D gamma ray images. That imaging is crucial in helping understand what is happening inside the BOP and informing the approach moving forward. For example, it told engineers which valves and rams inside the BOP were closed and which were open, and it showed that a piece of drill pipe was stuck inside the BOP. Trying to determine what was wrong with the BOP without this information is akin to determining why your car has stopped running if you have no working gauges and can't open the hood.
• They strongly encouraged BP to collect additional pressure measurements, which were very valuable in interpreting the behavior of the well and BOP after each top kill and/or junk shot attempt, and ultimately those measurements helped the government and BP determine that the top kill was not going to work and that it was time to move on. The measurements also showed that the top kill attempts did not significantly erode the BOP.
• During the top kill attempts, the team suggested rechecking all of the hydraulics on the BOP, which BP did. As a result, one of the pipe ram valves closed more tightly and provided more resistance to the flow.
• The team conducted an extensive suite of structural analyses to assess the stability of the riser system in support of the choke and kill series.
• The team conducted an independent set of analyses to explain the oil and mud flow during the choke and kill series. This provided an understanding of the operational limits of the containment system going forward.
The list does not, however, appear to have been updated since June 15th.

After the visit today Admiral Allen issued the following statement:
"Today I met with Secretary Chu, Marcia McNutt and other scientists and geologists as well as officials from BP and other industry representatives as we continue to prepare and review protocols for the well integrity test - including the seismic mapping run that was made around the well site this morning. As a result of these discussions, we decided that the process may benefit from additional analysis that will be performed tonight and tomorrow.

Both the Helix Producer and the Q4000 collection systems are currently on line with the potential to exceed the containment capability that existed before the sealing cap was installed, and skimmers continue to be surged to the well site in anticipation of any increased oil flow as part of the transition. The drilling of relief wells also continues- the first relief has been drilled to a depth of 17,840 feet below the Gulf surface, and the second to a depth of approximately 15,963 feet below the surface."
The time of the more than 200 scientists and engineers that the Secretary has involved in these decisions is no doubt a part of the $99.7 million bill that the Administration presented to BP today. BP have already paid previous bills totaling $122.3 million to the Administration.

In today’s briefing the Admiral noted that the seismic run that was carried out this morning was to provide a baseline measurement of the seabed condition before the pressurization test of the well casing occurred. It also had to be carried out in daylight, since the vessel running the sensors had to steam through the fleet assembled around the well, and the sensors also were likely to be degraded by too much adjacent noise as they ran the scan.

He also corrected the sequence for the close down of the flows out of the well. (My concern yesterday) The sequence is
When we get ready to start the well integrity test, we will first cease production through the Q4000 and the Helix Producer I. We will then divert all the hydrocarbons up into the new capping stack. Valves through the kill and the choke lines for the new capping stack will be opened. And the center bore is already open. So we will be venting basically through three different exits on the capping stack, the kill line and the choke line, and the main line going through the bore.

Then in sequence we will attempt to close the stack down and assess the pressure readings. As we do that, the first thing we will do is close the main ram. There are three rams. The middle one will be closed and that will basically shut off the flow outward through the top of the capping stack. At that point we’ll take pressure readings. We will then close the kill line, which is the second remaining outlet and take pressure readings.

The third and most critical will be the choke line. There is a special device that has been built on the capping stack. You will see it. If you look at the video, it is yellow. It is long horizontally and it is a curved up pipe for the exit of the hydrocarbons. That choke line will be controlled by a remotely operating vehicle, which will slowly close it incrementally. And this is going to be very, very important because we want to measure the amount of closure, which will be measured gradually by turns of that choke line valve by an ROV simultaneously taking pressure readings.

The goal is to slowly close that down and understand the changes in pressure as we are closing it until that choke line is closed. At that point, there’ll be no hydrocarbons exiting from the capping stack. And we will go into a period where we’re going to start taking pressure readings. It will go in basically 6, 24, and 48 hour increments depending on the results.
Once the well is shut in then the pressure at the BOP (which is monitored by transducers and not the visible gages) should rise to between 8 and 9,000 psi (which Admiral Allen, a long time ago, had said was monitored just downstream of the BOP at the start of remediation). This is the anticipated value when the weight of the oil/gas column is subtracted from the pressure in the bottom of the well. Anything less than this will indicate that there may be some problems within the body of the well. Incidentally the gages that the ROVs are monitoring are monitoring pressures in the accumulator lines that run the hydraulics of the rams and power tools.

The Admiral was also more precise on the exact location of the relief well
Development Driller III is now at 17,840 feet measured depth. They’ve been there for a day or two. They are doing testing to make sure they have the right angle of attack as they close in for the last 60 or 70 feet before they’ll actually try and make the penetration for the relief well.

And the current estimate of how far away they are from the condo well at this point is four feet four inches. So you can imagine this gets pretty precise as they’re trying to go down another 60 or so feet and actually hit the point where they can drill into the annulus and potentially to a seven inch casing pipe. So that continues as well.
The Admiral noted that they are on pace to have 1,000 skimmers along the coast by the end of the month, and that they are using 2 million tyvek suits a month (the suits worn in cleaning the beaches) and there is a growing concern about the national supply of these.

And he pointed out that a part of the shut-down process will be visible
What we will do in sequence is we will stop production on the Q4000 and the Helix Producer I and remove the way for the hydrocarbons to exit through the kill and the choke lines on the original blow out preventer. That will move to three exit points, the choke and the kill lines of the capping stack and then the top opening of the capping stack. Then we will in sequence first, there are three rams that are a part of the capping stack. The middle ram will be closed. That will seal the upper opening from any hydrocarbon release. That will leave us the kill and the choke lines.

The kill line will then be closed as well. Now remember this is either open or shut. That will leave the choke line of the capping stack as a last way for hydrocarbons to exit from the capping stack. And that is set up with a specially designed engineered and built, you’ll be able to see it on the video. It’s a horizontal, yellow piece of equipment that has a pipe that curves up where the hydrocarbons would exit and at the other end there’s a place to insert a tool with a remotely operated vehicle and then slowly close the valve, which we will do that while we are taking pressure readings.
This is the control panel he was talking about, taken at 5 pm Eastern.


BP is also now holding twice daily briefings. In the morning one Kent Wells gave the actual timeline for the 3-ram stack installation
First in terms of the capping stack, last night at 6:20 pm we actually landed the stack on top of the transition spool. By 7:00 we had it fully connected and sealed on top of that device. And then at 8:30 we actually disconnected the drill pipe from the drill ship enterprise from it and so it was in place and free standing at that point in time.
The tests of the flow to the Helix Producer showed that it could sustain flows of up to 12,500 bd (as high as they went) He slightly corrected the Admiral on the relief well:
The first relief well is at 17,840 feet. Right now we’re running another survey to confirm the distance from the Macondo well, the direction from the Macondo well and the inclination of it.

We only have another 30 feet to drill before our final casing point and so we want to make sure that this well is perfectly lined up. So that’s why we’re doing this confirmation run. We’ll do that then we’ll trip back in the hole and we’ll drill that final 30 feet. Then we’ll come back in and what we call open up the hole to make it large enough to run the casing and most likely we’ll be running casing in the hall on Sunday, but of course there can be variability to that. But what I would say is that we’re on track and I’m still looking for the most likely intercept of the Macondo well being at the end of July.
He went on to say, in regard to that intersection
So the inclination we’re looking for at the bottom is somewhere in the range of two to two and a half degrees and we think we’re in that range, we just want to confirm that. And that lines us up as we then – after we set the casing I’ll come back and talk about that in a second. We’ll have about 100 to 150, 200 feet to drill to intersect and that two degree angle allows us to do that in that period of time. So that’s why we want that particular angle.

In the afternoon briefing he pointed out that when the sequence of tests on the 3-ram stack begins:
down below two rams there’s a what we call our flow T and there’s two sides to it and that’s where the flow would be coming out when we actually shut one of the rams.
However, as I pointed out at the start of this post (and as still holds true) the integrity test has yet to be initiated.

Read more!